Portfolio

Project Name

MERCEDES BENZ SHOWROOM , ADITYAPUR

Challenges : Mainly structural repair of entire showroom. Repair work of RCC coloumn , water tank and retaining wall . Washing of room and some internal finishing (decorative painting ) was also done.

Duration of Work : 4 months

Value : 10 lacs

VIRDI NIWAS , BISTUPUR

Challenges : Renovation job of the entire building. Structural strengthening was done by proving Rcc Columns , which was not present previously. The entire structure stands on bricks , hence inputs were taken from Mr.Khan ( Dept of Civil Engg, NIT Jamshedpur ). Some internal/external wall repairing was also carried out.

Duration of Work : 8 months

Value : 30 lacs

TML Hospital

Challenges : C.T Scan room , FRE EXIT Ramp and water tank pump room.

Duration of Work : 240 days.

Value : 1.25 Cr

P 15 ,P 16  ( 16 blocks)

Challenges : Columns and beams tested in lab before starting of work . After approval from specialised agencies , the reinforcement work of Ree columns ( by micro-concreting ) and beams carried out. Other tasks include re-plastering , kitchen modification , roof treatment , wooden and plumbing work.

Duration of Work : 180 days.

1.15 Cr ( 45lacs Civil Work + 70lacs Chemical Work ) .

J/ U TYPE            ( J 43– J48 )

Challenges : Blocks in poor condition with balconies tilted , heavy seepage , bulky plasters and absence of RCC Columns. Work was carried out to RCC structures ( i.e ceilings , beams , stairs ) by BASF , plumbing & wooden work and merging of 2 blocks in one. Thus 16 blocks were modified to EIGHT.

Duration of Work : 150 days for each block.

Value : 40-45 lacs .

N TYPE , TATA MOTORS             ( N91– N94  ,  N 26– N28 )

Challenges : Water seepage from roof due to weakened rcc coloumns and poor condition of entire external plaster. Chemical treatment of RCC Structure by BASF and FOSROC , replastering and waterproofing was carried out. Also compound chemical treatment of toilets , changing of doors ( use of Century ply 30mm thick doors with branded fittings) and major kitchen room modification was done. Another major task was to change the entire plumbing system ( use of 2000 ltrs Syntex tanks ) .

Duration of Work : 90 days for each block.

Value : 25-26 lacs per block